S75 at S Nöldnerplatz

Frequency Change Upcoming Nights only

Lichtenberg <> Nöldnerplatz

Reason: Point maintenance work in Lichtenberg

Starts Wed 25 Nov 2026, 22:00 starts in 8 days
Planned end Fri 27 Nov 2026, 01:30
Total duration 2 closures, 7 hours in total

What is affected

  1. Tact change: Lichtenberg <> Nöldnerplatz: S-Bahn services are running only at 6- and 14-minute intervals towards Ostkreuz (into the city) and at 3- and 17-minute intervals towards Lichtenberg (out of the city) on lines S5 and S7.

When exactly

  • Daily 22:00–01:30 Wed 25 Nov → Fri 27 Nov 2026 Fri 27 Nov 2026

Affected section

Also affects: S5, S7

Route information
  1. The S5 runs between Strausberg Nord and Strausberg <> Westkreuz
  2. Every 10 minutes: Mahlsdorf <> Wuhletal
  3. S7 runs between Ahrensfelde <> Potsdam Central Station
  4. Every 10 minutes: Nöldnerplatz <> Westkreuz
  5. S75 runs between Wartenberg <> Lichtenberg