Back to S Wartenberg’s calendar
No Service
Ended
Reparatur an einem Signal in Friedrichstraße beendet
Started
Mon 17 Aug 2026, 11:25
Ended
Tue 18 Aug 2026, 11:44
ended 3 months ago
Total duration
24 hours
What is affected
Trains do not run on this route during this period.
Affected section
Also affects:
S3 , S5 , S7
No Service
Ended
Reparatur an einem Signal in Savignyplatz beendet
Started
Tue 18 Aug 2026, 09:45
Ended
Wed 19 Aug 2026, 10:01
ended 3 months ago
Total duration
24 hours
What is affected
Trains do not run on this route during this period.
Affected section
Also affects:
S3 , S5 , S7
No Service
Ended
Reparatur an einer Weiche in Charlottenburg beendet
Started
Tue 18 Aug 2026, 11:15
Ended
Wed 19 Aug 2026, 11:31
ended 3 months ago
Total duration
24 hours
What is affected
Trains do not run on this route during this period.
Affected section
Also affects:
S3 , S5 , S7
No Service
Ended
Polizeieinsatz in Hohenschönhausen beendet
Started
Tue 18 Aug 2026, 14:00
Ended
Wed 19 Aug 2026, 14:16
ended 3 months ago
Total duration
24 hours
What is affected
Trains do not run on this route during this period.
Other current & upcoming disruptions
Past disruptions of S75 at S Wartenberg
38 past →