S5 at S+U Warschauer Straße

Train Service Changed Upcoming

Kaulsdorf > Warschauer Straße

Reason: Track works

Starts Fri 20 Nov 2026, 21:45 starts in 3 days
Planned end Mon 23 Nov 2026, 01:30
Total duration 2 days

What is affected

  1. Timetable change:
  2. During night services on Fri/Sat and Sat/Sun, the S5 runs from Kaulsdorf to Warschauer Straße 5 to 6 minutes later.

Affected section

Train Service Changed Upcoming

Friedrichstraße <> Alexanderplatz <> Ahrensfelde

Reason: Construction work

Starts Sat 21 Nov 2026, 16:00 starts in 4 days
Planned end Mon 23 Nov 2026, 01:30
Total duration 34 hours

What is affected

  1. Please note the changes to departure times and platforms (see train service information).

Affected section

Also affects: S3, S7, S9

Information on train services
Timetable change:
  1. The S3 to Erkner, the S5 to Kaulsdorf and the S9 to BER Airport will run 1 minute earlier from Friedrichstraße to Alexanderplatz.
  2. During daytime service, the S7 from Friedrichstraße to Ahrensfelde departs 10 minutes later (no change to night-time service on Sat/Sun). Trains from Ostbahnhof to Ahrensfelde will also run 10 minutes later to match this schedule.
Platform change:
  1. At Ostbahnhof, trains starting there and bound for Ahrensfelde (departing Ostbahnhof at 10, 30, 50) will depart from platform 10, on the city-bound platform.

Other current & upcoming disruptions

Past disruptions of S5 at S+U Warschauer Straße 85 past →